*Please note – at this time all dates are estimated and subject to change, unless noted as "CONFIRMED".  Please stay tuned for public notices.

  • December 2017 – Article 10 – File Final Public Involvement Program Plan with Siting Board
  • May 29, 2018 – Article 10 – File Preliminary Scoping Statement with Siting Board – 21-day public comment period - CONFIRMED
  • June 2018 – Article 10 – Intervenor Funding Made Available to Municipal and Local Parties - CONFIRMED
  • June–July 2018 – Article 10 – Nominations Considered for Local Members of Siting Board - CONFIRMED
  • July 6, 2018 – Public Comments on Preliminary Scoping Statement Due - CONFIRMED
  • September 2018 – NYISO Interconnection Studies Complete
  • October 2018 – Article 10 – Full Application Submitted to Siting Board
  • October 2018 – Open House
  • December/January 2018 – Article 10 – Full Application Deemed Compliant
  • Calendar Year 2019 – Article 10 – Adjudicatory Process – Public Hearings
  • Late December 2019 – Article 10 – Siting Board Decision
  • Late December 2019 – Commence project procurement and construction
  • 3rd Quarter 2020 – Commence Facility Operation